1. Home
  2. PMI
  3. PMP Exam Questions

Free PMP Exam Questions - PMI PMP Exam

PMI PMP Exam

Project Management Professional (2023)

Total Questions: 369

PMI PMP Exam - Prepare from Latest, Not Redundant Questions!

Many candidates desire to prepare their PMI PMP exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the Project Management Professional (2023) exam, our team of experts updates PMP questions and eliminates outdated questions. In this way, we save you money and time.

Do Not Fall for Cheap and Old PMI PMP Exam Questions

Study4Exam offers Premium High-Quality Exam Questions

Find out what will be covered on the exam and how it will be presented so you can prepare adequately. You can better prepare for the PMI PMP exam by familiarizing yourself with the types of questions and topics covered on the exam. Don't squander your time studying irrelevant material; instead, focus on what will be on the actual Project Management Professional exam.

Not Just Questions - Get Real PMI PMP Exam Experience

Create a schedule that allows you to devote sufficient time each day to studying for the Project Management Professional (2023) exam. Try to cover the complete syllabus of the Project Management Professional exam. Do a self-assessment of preparation to know your weak spots. Fill these gaps in your preparation with our preparatory material and ace your exam on the first attempt.

PMI PMP Questions

Q1.

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?

Q2.

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

Q3.

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Q4.

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

Q5.

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

Solutions:
Question: 1 Answer: C
Question: 2 Answer: B
Question: 3 Answer: B
Question: 4 Answer: C
Question: 5 Answer: A

Limited Time Offer

50%

Off

Get Premium PMP Questions as Interactive Practice Test or PDF

Get Full Access for PMI PMP questions with 50% exclusive Discount

Get All Questions

Note: If you see any error in these PMI Project Management Professional (2023) questions or answers, get in touch with us via email: support@study4exam.com.

PMP Valid Dumps | Project Management Professional Exam Questions

PMP Exam Details

PMP Exam Syllabus

Disscuss PMI PMP Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!