1. Home
  2. PMI
  3. Free PMI-SP Exam Practice Questions

Free PMI-SP Exam Practice Questions

PMI-SP Exam

PMI Scheduling Professional

Total Questions: 326

Focus Only on What Matters For PMI-SP Exam Preparation

Many candidates desire to prepare their PMI-SP exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the PMI Scheduling Professional exam, our team of experts updates PMI-SP questions and eliminates outdated questions. In this way, we save you money and time.

PMI-SP Exam Sample Questions & Answers

Q1.

Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?

Q2.

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

Q3.

with an appropriate phrase.

The _______contains the schedule components and the rules for relating and using the components

to represent the process for completing a project.

See the explanation below.

A scheduling tool consists of the schedule components and the rules for connecting and using the

components to characterize

the process for completing a project. It is used to gather the schedule model and provide the means

of adjusting various parameters and

components that are typical in a modeling process.


Q4.

You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?

Q5.

What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?

Solutions:
Question: 1 Answer: B
Question: 2 Answer: C
Question: 4 Answer: D
Question: 5 Answer: D
Trustpilot
Based on 241 reviews
4.4 | Excellent
PMI-SP exam-style questions

I used the PMI PMI-SP course on study4exam for exam prep. It helped me practice exam-style questions and understand where I needed to study before test day.

Dmitri Volkov, 10 days ago
PMI-SP exam questions

These free PMI-SP exam questions are not enough for complete prep. Full questions bank necessary for executive-level understanding.

Olga Volkova, 5 days ago
PMI-SP exam sample questions

Free PMI-SP exam sample questions are ok but the full question bank showed depth needed.

Marco Giordano, 3 days ago
PMI-SP exam prep

This site was very helpful. I did my PMI PMI-SP exam on the 28th of May and I passed. Most questions were exactly what is on this site. Thank you study4exam for these helpful questions.

Ana Silva, 11 days ago
PMI PMI-SP questions

Tried the 5 free PMI PMI-SP questions first. Questions seemed easy. Thought I didn't need the paid version. Then I realized the exam was way harder. Bought a full question bank. These questions help me to pass my exam. Thanks Study4Exam!

James Mitchell, 2 hours ago
PMI-SP Exam questions

Tried free questions felt insufficient but bought full PMI-SP Exam questions bank helped us to pass the exam confidently.

Richard Thompson, 4 days ago
PMI-SP sample questions

Honestly, this site saved me some last-minute panic. The PMI-SP sample questions were spot on and helped me focus.

Valentina Smirnov, 9 days ago
PMI-SP questions bank

Started with free. I felt confident. Failed miserably. Full PMI PMI-SP questions bank showed me what I was missing. Passed second attempt. A free sample doesn't prepare you for PMI-SP difficulty.

Marcus Thompson, 2 days ago
PMI-SP exam practice questions

One thing is best in PMI-SP exam practice questions every answer has a detailed explanation.

Henrik Larsson, 6 days ago
PMI-SP practice papers

Thank you for the useful collation of mostly free PMI-SP practice papers, quite a lot of the questions are very relevant!

Yuki Nakamura, 13 days ago
PMI-SP questions

I passed PMI PMI-SP - 75 % Almost all of the questions were from Study4Exam.

Ingrid Hansen, 12 days ago
PMI-SP practice questions

Free PMI PMI-SP practice questions were basic. Upgraded to full prep. The complete question bank covered each exam topic I never imagined. Free won't cut it. Full prep is essential.

Sarah Chen, 27 hours ago
PMI-SP practice questions

i never pass my PMI-SP exam if I'm not use PMI-SP practice questions in my prep

Carlos Mendez, 8 days ago
×
avatar

Review details

Country · 1 review

Unprompted review
Trustpilot
Disscuss PMI-SP Topics, Questions or Ask Anything Related
0/2000 characters

Currently there are no comments in this discussion, be the first to comment!