1. Home
  2. PMI
  3. PMI-PBA Exam Questions

Free PMI-PBA Exam Questions - PMI PMI-PBA Exam

PMI PMI-PBA Exam

PMI Professional in Business Analysis

Total Questions: 200

PMI-PBA Exam - Prepare from Latest, Not Redundant Questions!

Many candidates desire to prepare their PMI-PBA exam with the help of only updated and relevant study material. But during their research, they usually waste most of their valuable time with information that is either not relevant or outdated. Study4Exam has a fantastic team of subject-matter experts that make sure you always get the most up-to-date preparatory material. Whenever there is a change in the syllabus of the PMI Professional in Business Analysis exam, our team of experts updates PMI-PBA questions and eliminates outdated questions. In this way, we save you money and time.

Do Not Fall for Cheap and Old PMI-PBA Exam Questions

Study4Exam offers Premium High-Quality Exam Questions

Find out what will be covered on the exam and how it will be presented so you can prepare adequately. You can better prepare for the PMI-PBA exam by familiarizing yourself with the types of questions and topics covered on the exam. Don't squander your time studying irrelevant material; instead, focus on what will be on the actual Professional in Business Analysis exam.

Not Just Questions - Get Real PMI-PBA Exam Experience

Create a schedule that allows you to devote sufficient time each day to studying for the PMI Professional in Business Analysis exam. Try to cover the complete syllabus of the Professional in Business Analysis exam. Do a self-assessment of preparation to know your weak spots. Fill these gaps in your preparation with our preparatory material and ace your exam on the first attempt.

PMI PMI-PBA Questions

Q1.

After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

Q2.

The requirements traceability matrix should primarily be used to:

Q3.

A business analyst has been assigned to a project that will design and build two new bridges and. at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

Q4.

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

Q5.

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release

Which is a possible reason why the requirement was not implemented?

Solutions:
Question: 1 Answer: A
Question: 2 Answer: D
Question: 3 Answer: D
Question: 4 Answer: D
Question: 5 Answer: A

Limited Time Offer

50%

Off

Get Premium PMI-PBA Questions as Interactive Practice Test or PDF

Get Full Access for PMI PMI-PBA questions with 50% exclusive Discount

Get All Questions

Note: If you see any error in these PMI Professional in Business Analysis questions or answers, get in touch with us via email: support@study4exam.com.

PMI Business Analysis | PMI-PBA Valid Dumps | Professional In Business Analysis Exam Questions

PMI-PBA Exam Details

PMI-PBA Exam Syllabus

Disscuss PMI PMI-PBA Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!